Business · AI data centers
Amazon sells control of 13 new data centers to Blackstone's trust, then rents all of them back
The $5 billion deal covers 647 megawatts in Indiana and Mississippi and has not closed yet. It shows how the AI building boom is being paid for: cloud giants build the facilities, sell them to investors, and keep using them on long leases.
Written 4 min read · 35 sources
On November 16, Blackstone Digital Infrastructure Trust, which trades on the New York Stock Exchange as BXDC, said it had signed a definitive agreement to buy a majority interest in two joint ventures with AWS. The deal values the portfolio at about $5 billion at a 7.0% initial cap rate. It is the trust's first investment since it went public.38
Not quite a purchase
The first headlines, including Bloomberg's, said Blackstone's trust would simply buy Amazon's data centers. The deal is narrower than that. Amazon puts the buildings into two joint ventures. BXDC takes a controlling stake in those ventures, AWS keeps the rest, and AWS leases back the whole portfolio.11112
Accounts differ on the exact size of the stake. Blackstone's press release and its filed transaction summary say 75%. Datacenterfeed, The Economic Times and WebProNews report 75.1%, and WebProNews puts AWS's remaining share at 24.9%. These accounts don't really conflict. The 75% figure is most likely rounded down from 75.1%, though Blackstone's own headline materials don't say so.3491011
The buildings are what the industry calls powered shells: finished structures with power and cooling in place, where the tenant installs its own servers. Blackstone calls the portfolio stabilized, meaning it is fully leased and earning rent from the first day. Some reporting says nine of the buildings are in Indiana, in the greater Chicago data-center market, and four are in Mississippi. None of the coverage reviewed names a town or county.379
Blackstone's transaction summary doesn't name the tenant. It describes it only as a high-investment-grade cloud provider rated AA by S&P. The lease is triple-net, meaning the tenant pays taxes, insurance and maintenance. The initial term is 12 years, extendable to 32, and rent rises 2.75% every year. At a 7% cap rate on $5 billion, first-year income comes to roughly $350 million. Reporting identifies the tenant as AWS, and Datacenterfeed reports that Amazon.com guarantees the leases.4911
For Blackstone's investors, this is close to a bond backed by one of the world's richest companies, with raises built in for more than a decade.
Taken together, that is what the trust is buying: income that rises on a fixed schedule from a single tenant with the credit standing of a large sovereign borrower, from buildings it doesn't have to operate. The 7% yield is generous for a tenant this strong, and that tells you how much Amazon values cash today over the buildings themselves.
Why Amazon wants the cash
Amazon's capital spending for 2026 has been reported at about $220 billion. In March it reportedly sold about $54 billion of bonds, and analysts then raised their forecasts for how much debt the biggest cloud companies will issue. Set against that, a $5 billion sale is a small slice of one year's construction budget. One tech outlet calculated that it covers about five days of Amazon's capital spending.333414
Selling buildings and leasing them back is now a standard way for big tech to raise money for AI construction. Meta, for example, reportedly set up a $14 billion joint venture with BlackRock for a data-center campus in El Paso and kept 20%. These deals turn buildings into cash now, in exchange for decades of rent.34
The rent on this deal is fixed and Amazon guarantees it, so the risk sits with Amazon. It still owes the payments even if AI demand cools. Those payments are a long-term obligation, whatever form the accounting gives them.
From signing to the deadline
- Nov 11, 20265
Earliest event date in BXDC's 8-K filing, which points to the agreement being signed that day.
- Nov 16, 202635
Blackstone announces the $5 billion agreement and files a Form 8-K.
- Fourth quarter 2026123
Closing expected, subject to customary conditions.
- Dec 31, 20269
Reported date after which either side can walk away if the deal hasn't closed.
Several figures are still only reported. Some outlets say BXDC will put in about $1.9 billion of its own equity and borrow about $2.5 billion in mortgage debt secured only by the buildings. They say Amazon will receive roughly $4.3 billion to $4.4 billion in cash, and that a side that fails to close when required would owe a $150 million fee. The transaction summary reviewed doesn't show how the deal is financed. BXDC shares reportedly rose on the news, but no report says by how much.32
Known
Unknown
- How much cash Amazon receives at closing, and how BXDC's side is financed.
- The towns or counties where the campuses sit.
Next
- A closing announcement from Blackstone before the reported December 31 deadline.
- Any word of a delay, extension or termination after the year turns.
Sources34
Crypto Briefing
Blackstone
wsj.com
The Times of India
Quartz
Bloomberg.com
bloomberglaw.com
Bisnow
- +9 more outlets
HeyDay News
Every source, by outlet
35 sources from 34 outlets· Most cited first
AI Weeklyaiweekly.co1
American Buildoutamericanbuildout.com1
Bisnowbisnow.com1
Blackstoneblackstone.com1
Bloomberg.combloomberg.com1
bloomberglaw.com1
CRE Dailycredaily.com1
- First reported
- Blackstone's BXDC Buys 75% of Amazon Data Centers
Credence Researchcredenceresearch.com1
Crypto Briefingcryptobriefing.com1
As aired
- Amazon is selling control of 13 brand-new data centers, then renting every one of them back.
- The deal values them at about five billion dollars. And it shows how the AI building boom is being paid for. Cloud giants build the facilities, sell them to investors for cash, and keep using them under long leases.
- What's still open is whether it closes before a year-end deadline, and how much cash Amazon actually walks away with.
- The buildings are what the industry calls powered shells. They're finished, with power and cooling already in place, and the tenant brings its own servers. There are 13 of them, with 647 megawatts of capacity, on two Amazon Web Services campuses.
- One campus is in northern Indiana, the other in Mississippi. Nine buildings are reportedly in Indiana, in the greater Chicago data-center market, and four are in Mississippi. Nobody has named the towns or counties.
- The first headlines said Blackstone would simply buy Amazon's data centers. The deal is narrower. Blackstone Digital Infrastructure Trust, which trades on the New York Stock Exchange as BXDC, is taking a controlling stake in two joint ventures that own the buildings. Amazon keeps the rest. It's the trust's first investment since it went public.
- Blackstone puts its stake at 75 percent. Other accounts put it at 75.1, with Amazon keeping 24.9. The rounder number is most likely just rounded.
- Amazon puts the buildings into two joint ventures. Blackstone's trust buys control of them, and Amazon Web Services leases back the entire portfolio. Blackstone calls it stabilized, meaning it's fully leased and earning rent from day one.
- The lease runs 12 years at first and can stretch to 32. Rent rises 2.75 percent a year. It's triple-net, so the tenant pays taxes, insurance and maintenance. At a 7 percent initial cap rate, five billion dollars works out to roughly 350 million dollars of first-year income.
- Blackstone's filing names the tenant only as a top-rated cloud provider, rated double-A. Amazon.com reportedly guarantees the leases. For Blackstone's investors, it's close to a bond backed by one of the world's richest companies, with raises built in for more than a decade.
- This deal still has to close before the year runs out, and we'll keep following it until it does. Subscribe to this channel, and find more at heyday dot news.
- Amazon's motive is cash. Its capital spending this year has been reported at about 220 billion dollars, and it reportedly sold about 54 billion dollars of bonds in March. Against that, this five billion dollar sale is a small slice of one year's construction budget.
- Big tech companies are borrowing heavily to fund AI construction, and deals like this have become a standard tool. Meta reportedly set up a 14 billion dollar joint venture with BlackRock for a data-center campus in El Paso, and kept 20 percent.
- These deals turn buildings into cash now, in exchange for decades of rent. Critics of the wider AI financing boom warn that structures like these push obligations off company balance sheets. None of those warnings targeted this deal.
- The money behind the deal is still only reported. Blackstone's trust would reportedly put in about 1.9 billion dollars of its own equity, plus about 2.5 billion in mortgage debt secured by the buildings alone. Amazon would reportedly receive 4.3 to 4.4 billion dollars in cash.
- The agreement was signed November 11 and announced five days later. Closing is expected in the fourth quarter, subject to the usual conditions. Either side can reportedly walk away if it hasn't closed by December 31, and a side that fails to close when required would owe a 150 million dollar fee.
- BXDC shares rose on the news, though by how much hasn't been reported. The deal is done only when Blackstone announces it has closed, and the reported deadline for that is December 31.