Lumaktaw sa nilalaman

UmuusadAraw 16

Gila River flooding from Painted Rock Dam releases

  1. Update 2 sa 2PinakabagoAraw 16Pagkalipas ng 14 araw

    Gila River flooding puts crossings at risk as dam releases continue

    The hazard forecast earlier this month is now active below Painted Rock Dam. A warning through November 30 does not set a reopening date for river crossings.

    Manood

    KYMA

    • ~3,000 cfsContinuing releases from Painted Rock Dam
    • Near 10 feetDownstream gauge stage, not road depth
    • Nov. 30, 3 p.m.Warning expiration, Mountain Standard Time
  2. Update 1 sa 2Araw 3

    Painted Rock releases could reach 3,000 cfs, putting Gila River crossings at risk

    Planned releases are set to rise twelvefold, threatening low-water crossings along the Gila River. Downstream effects could outlast the November 17 warning.

    Manood

    24X7 News

    • Planned rise to 3,000 cubic feet per second, with releases continuing until the reservoir is empty.

Sino ang nag-ulat

Sino ang nag-ulat

18 outlet · 38 sanggunian

10 sa 18 ang nakapag-ulat na sa puntong ito

Kronolohiya

Kronolohiya

Araw 16 · 2 ulat

  1. Unang nag-ulat

  2. Initial release scheduled at 250 cubic feet per second.

  3. Planned increase to 500 cubic feet per second, holding until Thursday morning.

  4. Planned rise to 3,000 cubic feet per second, with releases continuing until the reservoir is empty.

Sino ang sangkot

Sino ang sangkot

Mga organisasyon

  • National Weather ServiceU.S. forecasting agency of the National Oceanic and Atmospheric Administration
  • United States Army Corps of Engineersdirect reporting unit and U.S. Army's branch for military engineering

Mga lugar

  • Dateland
  • Maricopa County
  • Painted Rock Dam

Talakayan

Talakayan

Ang mga post dito ay para sa “Gila River flooding from Painted Rock Dam releases” at lumalabas sa bawat ulat nito.

Gila River flooding puts crossings at risk as dam releases continue