Aggiornamento 1 di 1UltimoGiorno 2
250MW left on Moyle link as fault narrows Northern Ireland’s winter options
The Moyle Interconnector is down to 250 megawatts with no restoration date announced. SONI’s supply reassurance depends on repairs and the availability of generating stations.
Cosa sapevamo all'inizio
- 250MWTransfer capacity remaining after the fault
- 50%Reduction in the link’s reported capacity
- 500MWEngineering capacity each way, subject to limits
- Mutual Energy reports 250 megawatts of remaining capacity and has activated recovery protocols.
Allora ancora aperto
- The underlying cause, first-confirmation date and timetable for restoring full capacity remain unestablished.
Cosa avevamo detto di seguire
- Watch for a dated operator update changing the transfer limit or setting out the repair plan, alongside confirmation of SONI’s applicable seasonal assumptions.
