Supreme Court Lets $400M White House Ballroom Build Continue — For Now
A Friday stay by Chief Justice Roberts and a 5-4 order ten days later let Trump's $400 million ballroom keep rising while courts weigh who could authorize it.
Co się zmieniło
- Chief Justice Roberts on Aug. 21, 2026 stayed a district-court halt due that evening.
- The full Supreme Court on Aug. 31, 2026 voted 5-4 to keep above-ground work going during litigation.
- The Trust sued Dec. 12, 2025 after East Wing demolition began Oct. 20, 2025, citing four federal legal theories.
Wtedy jeszcze otwarte
- No final ruling on whether the ballroom required express planning approval or violated environmental and property law.
- No confirmed total cost beyond the consistently reported $400 million, and no confirmed final size beyond the 90,000 square feet in sourced legal reporting.
Na co mieliśmy zwracać uwagę
- Whether the merits court reaches the planning and Property Clause claims before construction moots the practical remedy.
- Whether the administration's national-security rationale survives full briefing and argument.