China’s Antelope Reef Moves From Land-Building Toward a Runway
September satellite images add grading, stockpiles and supply activity to an emerging runway project. A 2027 landing forecast remains an analyst’s estimate, not a confirmed opening date.
Co wiedzieliśmy na początku
- Vantor imagery shows grading, material stockpiles, compaction equipment, a loaded gravel barge and a new wharf.
Wtedy jeszcze otwarte
- The apparent runway’s final dimensions, a comprehensive current paving inventory and its intended operating role remain unestablished.
- No completed runway, first landing or confirmed fuel and ammunition works are established.
Na co mieliśmy zwracać uwagę
- Watch whether paving occurs during the forecast first half of 2027, when any first landing is recorded, and whether military-support works or an official explanation of the site’s role emerge.