On 7 October 2026, the High Court dismissed MACH Energy’s appeal, leaving invalid the approval for a 22-year extension of the Mount Pleasant mine. The ruling’s immediate legal process remains open because the planning commission’s reconsideration of the extension approval is not reported as resolved; the mine can continue operating.

Seguir por RSS

Acompanhamento da históriaDia 1

1 reportagem0 veículo0 fonte

A história até agora

Histórico

  1. Aberta1 reportagem

Quem está envolvido

Pessoas

  • James EdelmanAustralian judge1 reportagem

Organizações

  • High Court of Australiahighest court of jurisdiction in Australia1 reportagem

Lugares

  • High Court of AustraliaParkes Pl, Parkes ACT 2600, Australia1 reportagem
  • THIESS Mount Pleasant Operation1100 Wybong Rd, Muswellbrook NSW 2333, Australia1 reportagem

Todos os veículos que lemos sobre esta história

0 fonte0 veículo