Midway Road’s rail waits have a planning budget—not an end date

A hill, short traffic queues and freight delays make the case for changing two CN crossings. The county has planning money—but no chosen design or construction funding.

Escrito 5 min de leitura · 14 fontes

Disponível em inglês

A driver heading north toward the Adolph railroad crossing can come over a hill with less room to see—and stop for—a line of waiting vehicles. From the other direction, a long southbound queue can reach back into the Highway 2 intersection. On this stretch of Midway Road, the problem is not simply how long a train takes to pass. It is where the waiting traffic has to go.⁠3

St. Louis County has brought residents into planning to eliminate two CN railroad crossings on the road in Hermantown and Midway Township. An introductory meeting on November 12, 2026, at the Aad Shrine Meeting and Event Center in Hermantown opened discussion of concerns and possible changes. It did not approve a bridge, tunnel or replacement road.⁠5

The distinction matters: the estimated $2,328,000 budget pays for planning and project development, not construction. No preferred solution has been selected, construction funding has not been awarded and there is no construction timetable. The county has money to work out what should be built—not yet to build it.⁠3⁠1

Two stops, with little room

The crossings are just over a mile apart on Midway Road, also designated County State Aid Highway 13, along the corridor between Interstate 35 and Highway 2. One is at St. Louis River Road. The other is in Adolph, only 0.2 mile south of Highway 2. CN owns and operates both, and each carries up to 30 trains a day. That is a maximum for each crossing, not evidence of 60 distinct trains using the corridor.⁠10⁠3

The hill roughly 0.4 mile south of Adolph restricts northbound drivers’ view of the back of a traffic queue. North of the tracks, the short distance to Highway 2 leaves limited space for southbound vehicles to wait. The county identifies both as safety concerns; these descriptions are not reports of a newly documented crash. Signals and gates, it also notes, do not eliminate the possibility of a vehicle-train collision.⁠3

A trip can be interrupted at both crossings, while maintenance at either can cause further disruption. For an ambulance, fire engine or police vehicle, the delay can lengthen an emergency response. No quantified response-time improvement has been established for a design that has not yet been chosen.⁠3

The commercial stakes are substantial, too. Midway Road is an oversize and overweight freight route supporting the Duluth Port. The county’s November 2 announcement says freight trucks account for 15% to 20% of road traffic. Delays increase freight costs and associated emissions, extending the consequences beyond the drivers waiting at the gates.⁠3⁠4

The wait for motorists at these crossings causes more than just frustration. With so many vehicles carrying freight, there's an economic impact as well.

Keith Musolf 10

Musolf, the county commissioner whose district includes both crossings, made that assessment in March as commissioners advanced the planning consultant’s contract. It was an argument for developing alternatives, not an endorsement of a design already in hand.⁠10

The road-traffic figures need care. The county’s November 2 announcement puts daily traffic at the crossings at more than 6,500 vehicles. Its March 10 release described more than 7,000 vehicles on Midway Road, while WDIO’s November 13 report on the meeting gave a range of 7,000 to 9,000. The available accounts do not establish comparable count dates or road sections, so those numbers cannot demonstrate that traffic has fallen. Nor do they count how many vehicles trains actually delay each day.⁠4⁠10⁠5

A choice before a construction promise

The county is not starting from a blank sheet of public opinion. According to its November announcement, a 2023 exploration study used meetings and surveys and identified the crossings’ effect on travel times as the area’s top traffic concern. It also found openness to change among residents, businesses and other stakeholders. Support for examining options, however, is not consent to any particular route through the community.⁠4

Two broad approaches are now in view. The road could be rerouted, or a bridge or tunnel could separate vehicles from trains. That second approach is called grade separation: road and railway cross at different heights, rather than sharing a crossing where vehicles must stop. County project manager Victor Lund discussed those families of alternatives at the November meeting, WDIO reported. They remain options for study, not approved layouts.⁠5

Either approach brings questions that a general promise to “eliminate the crossings” cannot answer. Where would a realigned road run? Which properties would be affected? How would people reach homes and businesses? An overpass or underpass also needs a workable connection to the surrounding roads. Those are central tests of a proposal, not details to settle after the important decision.

The county plans four waves of engagement. The first gathers concerns and goals for the road, feeding a statement of the project’s purpose and need. The second presents feasible alternatives and their trade-offs. The third explains the recommendation and the reasons for choosing it. The fourth addresses the final layout, property impacts, access changes and implementation steps, according to Railway Supply’s November 14 account.⁠1

The intended participants extend beyond nearby residents. The county lists trucking interests, roadside businesses and community organizations alongside emergency responders, maintenance staff and planners. Agency participants include Hermantown, Midway Township, the Minnesota Department of Transportation, the Duluth-Superior Metropolitan Interstate Council, CN and the Duluth Port. A road that serves all those users needs more than a design that merely clears the tracks.⁠3

What the planning money buys

The federal Railroad Crossing Elimination award, made in January 2025, provides up to $1,862,400 for planning and project development. Minnesota’s Infrastructure Investment and Jobs Act Match Program contributes approximately $249,000, with approximately $217,000 left as the county’s responsibility. The state and county figures are rounded. None represents an announced construction budget.⁠1⁠4

Sambatek leads the consultant team, assisted by Bolton & Menk, LHB and Braun Intertec. Commissioners gave the Sambatek contract preliminary approval on March 10, 2026; by the November announcement, the county said it had hired the team. Its assignment is to produce a recommended roadway layout, a cost estimate and an environmental document for federal approval.⁠10⁠4

The November description names the Federal Railroad Administration as the environmental approving agency; the earlier March description also named the Federal Highway Administration. Completing that work would support a subsequent request for capital funding. It would not itself provide the money to construct the improvements.⁠4⁠10

The eventual project is intended to reduce road delays and could allow higher train speeds, but those remain prospective benefits. For now, the meaningful progress is a process in which residents can examine alternatives before one becomes the recommendation. Relief at the gates still depends on a defensible layout, an understood cost and a later construction funding award. There is no confirmed date when the waits will end.⁠1

Fontes7

Das fontes aqui citadas, WDIO.com foi a primeira a publicar, 2 dias antes da emissão desta reportagem. Seguiram-se mais 2 órgãos de comunicação social.

4 órgãos de comunicação social sem data:Engage St Louis CountyMaryland State Fire MarshalFox21Onlinesambatek.com

Todas as fontes, por órgão de comunicação social
Tal como emitido
  1. A hill cuts drivers’ view of stopped traffic near a Midway Road railroad crossing.
  2. Trains can interrupt a trip twice, slow freight and hold up emergency responders. St. Louis County is bringing residents into planning to eliminate both crossings.
  3. Which road layout can solve those problems, and how will the county pay to build it?
  4. The two CN crossings sit just over a mile apart, along the corridor between Interstate 35 and Highway 2. Midway Road runs through Hermantown and Midway Township, and CN owns and operates both crossings.
  5. One crossing is at St. Louis River Road. The other is in Adolph, just two-tenths of a mile south of Highway 2. That short stretch leaves limited room for southbound vehicles waiting at the tracks. A long line can back up into the highway intersection.
  6. A hill about four-tenths of a mile south of the Adolph crossing creates a different danger. Northbound drivers have less distance to see stopped vehicles and brake. Gates and signals still leave a risk of collisions between vehicles and trains.
  7. Maintenance at either crossing can disrupt travel too. And a delay for an ambulance, fire engine or police vehicle can lengthen an emergency response. The county wants a design that improves those conditions while keeping freight moving.
  8. County Commissioner Keith Musolf represents both crossings. He said in March that freight delays carry an economic cost. Midway Road supports the Duluth Port as a route for oversized and overweight loads, so these waits reach beyond everyday commuting.
  9. Idling and longer freight trips add costs and emissions. Between fifteen and twenty percent of vehicles using the road are freight trucks. A 2023 county exploration study found that longer and more frequent trains had increased delays. Public meetings and surveys identified the crossings as the area’s top traffic concern.
  10. The road-traffic figures vary: more than seven thousand in March, seven to nine thousand around the meeting, and more than sixty-five hundred in November’s county announcement. Different count dates or road sections could explain that variation. It doesn't show that traffic has fallen.
  11. Those figures describe road use, rather than how many vehicles trains delay. Each crossing carries up to thirty trains a day. The county’s earlier consultation found support for exploring changes, with the choice of a design still ahead.
  12. Residents joined the introductory planning meeting on November twelfth, 2026, at the Aad Shrine Meeting and Event Center in Hermantown. A virtual option was available. The county asked people about their concerns and their vision for the road’s future.
  13. The estimated planning budget is two million, three hundred twenty-eight thousand dollars. Federal funding provides up to one million, eight hundred sixty-two thousand, four hundred dollars. Minnesota adds about two hundred forty-nine thousand dollars, and the county about two hundred seventeen thousand.
  14. The federal award came in January 2025 through the Railroad Crossing Elimination program. Minnesota’s Infrastructure Investment and Jobs Act Match Program supplies the state contribution. Construction funding still has to be secured.
  15. Subscribe to this channel to follow the road alternatives, property impacts and construction funding decisions.
  16. A bridge or tunnel could carry vehicles above or below the railway. Engineers call that grade separation. Another approach would reroute Midway Road. The county hasn't selected a preferred solution, and each approach needs detailed study.
  17. A new alignment means deciding where the road would go and how people would reach homes and businesses. An overpass or underpass also needs a layout that works for the surrounding community. The eventual improvements are intended to reduce road delays and could allow higher train speeds.
  18. The county plans four rounds of engagement. First come concerns and goals, then feasible alternatives and their trade-offs. A third round explains the recommendation and why it was chosen. The fourth addresses the final layout, property impacts, access changes and implementation steps.
  19. Residents, businesses and trucking interests will participate alongside community organizations. The county also wants input from emergency responders, maintenance crews and planners. Agency participants include Hermantown, Midway Township, Minnesota transportation officials, the Duluth-Superior Metropolitan Interstate Council, CN and the Duluth Port.
  20. Sambatek leads the consultant team, assisted by Bolton and Menk, LHB and Braun Intertec. County commissioners gave the Sambatek contract preliminary approval on March tenth, 2026. By November, the county had hired the team.
  21. The team must produce a recommended roadway layout, a cost estimate and an environmental document for federal approval. The county’s March plan named both federal railroad and highway agencies in that approval process. Its November description names the Federal Railroad Administration.
  22. Completing that work would support a later request for construction money. The road’s final route, its effects on property and access, and the cost of building it still depend on the alternative chosen. Motorists, freight operators and emergency responders have no confirmed date for relief at the crossings.