Vineland data center air-permit suit threat

  1. Atualização 1 de 1Mais recenteDia 4

    A $1.07 million fine leaves Vineland’s data center air questions unresolved

    Sustain SJ’s federal lawsuit notice challenges air permits, pollution controls and public participation. The state’s earlier penalty has not established current compliance.

    Ver

    US EPA

    • New Jersey announced a $1.07 million penalty for installing and operating 62 natural-gas generators without required state permits.
    • Sustain SJ sent its notice of intent to sue over alleged federal Clean Air Act violations.

Quem noticiou

Quem noticiou

48 órgãos · 61 fontes

7 de 48 já tinham noticiado até este momento

Cronologia

Cronologia

Dia 4 · 1 reportagem

  1. Sustain SJ sent its notice of intent to sue over alleged federal Clean Air Act violations.

  2. Primeiro a noticiar

Quem está envolvido

Quem está envolvido

Organizações

  • EarthjusticeUS environmental litigation organization
  • New Jersey Department of Environmental Protectiongovernment agency of the U.S. state of New Jersey

Locais

  • 3963 South Lincoln Avenue
  • Vineland