Iowa Army Plant Lead-Azide Detonation

  1. Atualização 3 de 3Mais recenteDia 935 horas depois

    68 unstable drums, a stayed Iowa blast permit—and an unresolved emergency exception

    The Eighth Circuit's stay has no fixed expiration date. But EPA's argument for treatment without a permit leaves Monday consequential—and families without settled safety instructions.

    Ver

    Governor Kim Reynolds

    • Sixty-eight drums of unstable explosive sit at the Iowa Army Ammunition Plant—roughly five tons of stored material that the Army says is too dangerous to move. A federal appeals court has suspended the permit to destroy it in place. But nearby families still cannot treat the advertised Monday, November 23 operation as canceled: EPA argues that separate emergency authority could allow the Army to act without that permit. No court has approved that route, and no completed detonation has been established.
    • The weight of lead azide, the expected exposure levels, the EPA's risk assessment, and the standard that would trigger cleanup of a private yard.
    • Whether the permit's 15-mph limit applies to gusts or to sustained wind.
    • Whether sampling results, including any from Illinois, are made public.
  2. Atualização 2 de 3Dia 733 horas depois

    Army delays Iowa detonations to Monday, but key safety instructions remain missing

    The Army moved the blasts to November 23, citing unstable explosives and approaching cold. Families still need revised evacuation instructions—and answers about lead testing and cleanup.

    Ver

    The Independent

    • Sand barriers two stories high surround the barrels the Army plans to blow up in Middletown, Iowa. Concrete, buried soil, water sprays and air misting are meant to keep most of the lead on military property. Even with those precautions, the Army warns of a visible dust plume, ground vibration and explosions that could break nearby windows.
    • The weight of lead azide, the expected exposure levels, the EPA's risk assessment, and the standard that would trigger cleanup of a private yard.
    • Whether the permit's 15-mph limit applies to gusts or to sustained wind.
    • Whether sampling results, including any from Illinois, are made public.
  3. Atualização 1 de 3Dia 6

    Army to blow up 68 barrels of unstable explosive in Middletown, Iowa, sending lead dust toward Illinois

    The Army says the degraded lead azide is too dangerous to move. Its own modeling shows lead settling on surfaces up to about 40 miles downwind. Iowa learned of the plan four days before the blasts, and Illinois says the EPA office that approved it never told it.

    Ver

    MSF Switzerland

    • 68Barrels of degraded lead azide
    • ~100 miModeled airborne plume reach
    • ~40 miModeled reach of surface deposition
    • 24hDeadline to start post-blast soil sampling
    • EPA issues the emergency permit for in-place detonation.
    • Two controlled detonations scheduled.
    • The weight of lead azide, the expected exposure levels, the EPA's risk assessment, and the standard that would trigger cleanup of a private yard.
    • Whether the permit's 15-mph limit applies to gusts or to sustained wind.
    • The six-hour and hourly plume updates on Friday morning, and whether the wind holds the blasts back.
    • Whether sampling results, including any from Illinois, are made public.

Quem noticiou

Quem noticiou

71 órgãos · 137 fontes · 6 vídeos

40 de 71 já tinham noticiado até este momento

Quem noticiou o quê

Pontos noticiados por mais de um órgão de comunicação

Pontos noticiados por um só órgão de comunicação14

Noticiado apenas por Chicago Sun-Times

Noticiado apenas por CBS Minnesota

Noticiado apenas por The Independent

Cada linha é a afirmação tal como a registámos da reportagem desse órgão. Comparado a .

Cronologia

Cronologia

Dia 9 · 3 reportagens

  1. Primeiro a noticiar

  2. EPA issues the emergency permit for in-place detonation.

  3. 2 dias depois

  4. EPA public notice, with no comments accepted. Iowa's governor's office says the state learns of the plan after the Army's public advisory.

  5. Protest planned at the Armed Forces Reserve Center in Middletown.

  6. Two controlled detonations scheduled.

Quem está envolvido

Quem está envolvido

Pessoas

  • Kim ReynoldsGovernor of Iowa since 2017
  • Mike KehoeAmerican politician (born 1962)
  • Rob SandAmerican lawyer and politician and Governor-elect of Iowa (born 1982)
  • Sameer Vohra
  • Tammy DuckworthAmerican politician and military officer (born 1968)

Organizações

  • United States Armyland service branch of the United States Armed Forces
  • United States Environmental Protection AgencyU.S. federal government agency
  • EarthjusticeUS environmental litigation organization
  • Illinois Environmental Protection AgencyU.S. state government agency
  • Iowa Army Ammunition PlantFacility of the US Army Joint Munitions Command
  • Sierra Clubenvironmental nonprofit membership association based in the United States
  • State of Missourigovernment of the U.S. state of Missouri
  • United States Court of Appeals for the Eighth CircuitCurrent United States federal appellate court

Locais

  • Iowa Army Ammunition Plant
  • Middletown
  • Hannibal
  • Maquoketa
  • Mediapolis
  • Mississippi River
  • Muscatine
  • New Boston

Promessas

Promessas

Promessas nesta história: 2Vencida, ainda não verificada 2

  • Vencida, ainda não verificadaU.S. Army: The Army says it will use earthworks, soil wetting, air misting, and air monitoring to limit the release and spread of lead-containing dust.Prazo:
  • Vencida, ainda não verificadaU.S. Army: The Army says it will conduct air monitoring during the blast and sampling afterward to identify material that may need cleanup.Prazo:

Discussão

Discussão

As publicações aqui pertencem a «Iowa Army Plant Lead-Azide Detonation» e aparecem em todas as suas reportagens.

68 unstable drums, a stayed Iowa blast permit—and an unresolved emergency exception