Обновление 2 из 2ПоследнееДень 7164 дня спустя
Tasmania makes data centres pay communities—but lets companies run the funds
Major data centres would make recurring payments to their host communities. The rate is now clear; residents’ authority over company-administered grants is not.
СмотретьСамый ранний источникABC Tasmania
Что изменилось
- A$3,000Minimum annual contribution per MW of contracted firm demand
- A$300,000Annual minimum for 100MW contracted firm demand
- >20MWFacilities covered by the contribution requirement
Тогда оставалось открытым
- No names, exact sites beyond one northwest preference and one Bell Bay smelter interest, or timelines for the six.
- Correct moratorium petition total and what Tasmania gains in jobs or revenue.
- Hydro Tasmania’s end-of-year ruling on Firmus’s 450 MW request and whether any confidential load must fund new generation.
- Whether parliament’s inquiry turns draft expectations into binding guardrails before sites lock in.
