Cernavoda Unit 2 shutdown
DevelopingNext check : A report on Unit 2 resuming operation.
Where it stands
Cernavoda disconnected Unit 2 on 14 August 2026 as Danube levels fell extremely low after prolonged heat. With Unit 1 already shut down, the plant was fully offline, removing about 20 percent of Romania’s electricity supply; no return-to-service update is reported.
Story trackerDay 1
1 report11 outlets11 sources1 video
The story so far
Romania Loses a Fifth of Its Power as Danube Starves Nuclear Plant
Both 706 MW Cernavoda reactors shut over record-low Danube water, wiping out about a fifth of national power and forcing Romania to lean on imports.
Still open after this report
- No firm public restart date is established in the available sources.
- No verified basin-wide flow statistics or first-since date are established in the provided sources.
History
Opened1 report
Who's involved
Places
- Cernavoda Nuclear Power PlantStrada Medgidiei, 905200 Cernavodă, Romania1 report
- Danube RiverDanube1 report
- Paks Nuclear PlantPaks, hrsz 8803/17, 7030 Hungary1 report
- RomaniaRomania1 report
Every outlet we read on this story
11 sources11 outlets1 video
HeyDay News11 video
nuclearnewsnetwork.com1
romania-insider.com1
world-nuclear-news.org1