Cernavoda disconnected Unit 2 on 14 August 2026 as Danube levels fell extremely low after prolonged heat. With Unit 1 already shut down, the plant was fully offline, removing about 20 percent of Romania’s electricity supply; no return-to-service update is reported.
新聞追蹤第 1 天
1 篇報導11 家媒體11 個來源1 部影片
事件至今
Romania Loses a Fifth of Its Power as Danube Starves Nuclear Plant
Both 706 MW Cernavoda reactors shut over record-low Danube water, wiping out about a fifth of national power and forcing Romania to lean on imports.
本篇報導後仍無定論
- No firm public restart date is established in the available sources.
- No verified basin-wide flow statistics or first-since date are established in the provided sources.
經過
開啟1 篇報導
相關各方
地點
- Cernavoda Nuclear Power PlantStrada Medgidiei, 905200 Cernavodă, Romania1 篇報導
- Danube RiverDanube1 篇報導
- Paks Nuclear PlantPaks, hrsz 8803/17, 7030 Hungary1 篇報導
- RomaniaRomania1 篇報導
我們就此事閱讀過的所有媒體
11 個來源11 家媒體1 部影片
HeyDay News11 部影片
nuclearnewsnetwork.com1
romania-insider.com1
world-nuclear-news.org1