Tasmania's six proposed AI data centres

  1. 第 2 則更新,共 2 則最新第 71 天64 天後

    Tasmania makes data centres pay communities—but lets companies run the funds

    Major data centres would make recurring payments to their host communities. The rate is now clear; residents’ authority over company-administered grants is not.

    觀看

    ABC Tasmania

    • A$3,000Minimum annual contribution per MW of contracted firm demand
    • A$300,000Annual minimum for 100MW contracted firm demand
    • >20MWFacilities covered by the contribution requirement
    • No names, exact sites beyond one northwest preference and one Bell Bay smelter interest, or timelines for the six.
    • Correct moratorium petition total and what Tasmania gains in jobs or revenue.
    • Hydro Tasmania’s end-of-year ruling on Firmus’s 450 MW request and whether any confidential load must fund new generation.
    • Whether parliament’s inquiry turns draft expectations into binding guardrails before sites lock in.
  2. 第 1 則更新,共 2 則第 7 天

    Tasmania's Secret AI Load: 500 MW, No Names, No Water

    A tabled paper lists 10 AI centres and up to 1,150 MW of interest — but the six biggest newcomers have no names, mostly no sites, and no water figures.

    觀看

    ABC Tasmania

    • 1,770 MWTasmania system peak demand 2024-25
    • 505–705 MWCombined demand, six secret proposals
    • up to 1,150 MWPotential demand, ten-centre pipeline
    • Six confidential AI proposals would add roughly 505 to 705 MW if all proceeded.
    • Water use for all six is listed as not defined, unlike named Firmus figures.
    • Tasmania’s 2024-25 system peak was 1,770 MW.
    • No names, exact sites beyond one northwest preference and one Bell Bay smelter interest, or timelines for the six.
    • Correct moratorium petition total and what Tasmania gains in jobs or revenue.
    • Hydro Tasmania’s end-of-year ruling on Firmus’s 450 MW request and whether any confidential load must fund new generation.
    • Whether parliament’s inquiry turns draft expectations into binding guardrails before sites lock in.

報導媒體

報導媒體

40 家媒體 · 94 個來源 · 1 部影片

截至此時,40 家媒體中已有 12 家報導

相關各方

相關各方

人物

  • Felix EllisAustralian politician
  • Jeremy RockliffAustralian politician
  • Cecily RosolAustralian politician
  • Helen BurnetAustralian politician
  • Rosalie WoodruffAustralian politician and epidemiologist
  • Tabatha BadgerAustralian politician

機構

  • Government of Tasmaniastate government of Tasmania, Australia
  • Hydro Tasmaniahydro electricity developer, and electricity provider in Tasmania, Australia

地點

  • Tasmania
  • Bell Bay
  • Bell Bay
  • Burnie
  • George Town
  • Long Reach
  • Saint Leonards
  • Wesley Vale

承諾

承諾

本事件中的承諾:1未到期 1

  • 未到期Jeremy Rockliff: Rockliff said the expectations document would be reviewed within six months.期限

討論

討論

此處的貼文屬於「Tasmania's six proposed AI data centres」,會顯示在該新聞事件的每篇報導下。

Tasmania makes data centres pay communities—but lets companies run the funds