Gila River flooding from Painted Rock Dam releases

  1. به‌روزرسانی 2 از 2جدیدترینروز 16۱۴ روز بعد

    Gila River flooding puts crossings at risk as dam releases continue

    The hazard forecast earlier this month is now active below Painted Rock Dam. A warning through November 30 does not set a reopening date for river crossings.

    تماشا

    KYMA

    • ~3,000 cfsContinuing releases from Painted Rock Dam
    • Near 10 feetDownstream gauge stage, not road depth
    • Nov. 30, 3 p.m.Warning expiration, Mountain Standard Time
  2. به‌روزرسانی 1 از 2روز 3

    Painted Rock releases could reach 3,000 cfs, putting Gila River crossings at risk

    Planned releases are set to rise twelvefold, threatening low-water crossings along the Gila River. Downstream effects could outlast the November 17 warning.

    تماشا

    24X7 News

    • Planned rise to 3,000 cubic feet per second, with releases continuing until the reservoir is empty.

چه کسی گزارش کرد

چه کسی گزارش کرد

18 رسانه · 38 منبع

تا این لحظه 10 مورد از 18 مورد گزارش شده بود

خط زمانی

خط زمانی

روز 16 · 2 گزارش

  1. نخستین گزارشگر

  2. Initial release scheduled at 250 cubic feet per second.

  3. Planned increase to 500 cubic feet per second, holding until Thursday morning.

  4. Planned rise to 3,000 cubic feet per second, with releases continuing until the reservoir is empty.

چه کسانی درگیرند

چه کسانی درگیرند

سازمان‌ها

  • National Weather ServiceU.S. forecasting agency of the National Oceanic and Atmospheric Administration
  • United States Army Corps of Engineersdirect reporting unit and U.S. Army's branch for military engineering

مکان‌ها

  • Dateland
  • Maricopa County
  • Painted Rock Dam

گفت‌وگو

گفت‌وگو

پست‌های اینجا متعلق به «Gila River flooding from Painted Rock Dam releases» هستند و در همهٔ گزارش‌های آن دیده می‌شوند.

Gila River flooding puts crossings at risk as dam releases continue