The Moyle Interconnector capacity fault

  1. به‌روزرسانی 1 از 1جدیدترینروز 2

    250MW left on Moyle link as fault narrows Northern Ireland’s winter options

    The Moyle Interconnector is down to 250 megawatts with no restoration date announced. SONI’s supply reassurance depends on repairs and the availability of generating stations.

    تماشا

    BBC News

    • 250MWTransfer capacity remaining after the fault
    • 50%Reduction in the link’s reported capacity
    • 500MWEngineering capacity each way, subject to limits
    • Mutual Energy reports 250 megawatts of remaining capacity and has activated recovery protocols.
    • The underlying cause, first-confirmation date and timetable for restoring full capacity remain unestablished.
    • Watch for a dated operator update changing the transfer limit or setting out the repair plan, alongside confirmation of SONI’s applicable seasonal assumptions.

چه کسی گزارش کرد

چه کسی گزارش کرد

10 رسانه · 16 منبع

تا این لحظه 5 مورد از 10 مورد گزارش شده بود

چه کسانی درگیرند

چه کسانی درگیرند

سازمان‌ها

  • Department for the EconomyNorthern Ireland government department
  • Mutual EnergyEnergy company in Northern Ireland, United Kingdom

مکان‌ها

  • Northern Ireland
  • United Kingdom